How Many Pallets Does an AS/RS Need? A Reusable Pool Sizing Guide

Start with the flow of pallets through the whole loop, then add the ready reserve the operation decides it needs.

BAOHENG 7 min
Illustration of reusable blue plastic pallets beside a warehouse planning table
AI-generated editorial illustration based on a BAOHENG product reference; not an actual warehouse, counted inventory or recommended stack arrangement.
In this guide

To estimate a reusable AS/RS pallet pool, multiply the average number of pallet cycles started per day by the average time each pallet spends in the defined cycle. This gives an average number circulating in that cycle, not a guaranteed minimum purchase quantity. Add a separately planned ready reserve, subtract existing usable pallets from the resulting target, and plan how lost or retired pallets will be replaced. Use a consistent time basis throughout.

Our cost-per-trip guide compares operating costs after defining completed trips. This guide addresses a different purchasing decision: how many compatible pallets must be available across the loop and in reserve?

1. Draw the loop and choose the counting boundary

Choose one event at which a ready pallet is assigned to a new load as the start; the cycle ends when that same pallet is returned, inspected and ready for another assignment. Include all relevant stages in between: loaded handling, warehouse dwell, dispatch or unloading, empty returns and preparation. A closed loop inside one warehouse can be shorter; a loop involving an external customer may include waiting and transport outside the site. Draw the actual route rather than assuming either pattern.

Record pallet cycles started, not the number of conveyor moves or cartons. One pallet passing several stations is still one cycle. If some pallets leave the loop permanently or do not return, record them separately; a cycle-time average calculated only from prompt returns can hide the missing ones. Count each compatible pallet pool separately if different models or routes cannot be substituted for one another.

2. Match throughput and time units

Use data from the same defined loop and a representative, reasonably stable period. If throughput is measured per calendar day, include weekends and holidays in the cycle time; for working days, use a consistent working-day clock for both figures. A persistent backlog, seasonal ramp-up or planned closure makes a single steady average less representative; examine those periods separately and use a time-based stock projection for the actual peak or transition.

Average pallets in the cycle = average cycles started per day × average cycle time in days.

This is an application of Little’s Law to the selected boundary. MIT’s process-analysis material expresses the relation between average inventory, throughput and flow time; MIT’s transportation lecture identifies system stability as an assumption. The calculation estimates a long-run average in the chosen boundary. It does not predict a daily maximum or determine a service-level guarantee.

3. Worked example: a hypothetical closed loop

Assume a warehouse starts an average of 240 pallet cycles per calendar day. Its average time from allocation until ready for the next load is 2.5 calendar days. The stages below are illustrative averages for the same loop, not measured BAOHENG performance.

Stage Assumed average time
Loaded movement and storage 1.5 days
Unloading and empty return 0.6 days
Inspection and preparation before ready 0.4 days
Complete cycle 2.5 days

Average circulating pallets = 240 cycles/day × 2.5 days = 600 pallets. This includes pallets in inspection because inspection time is already in the 2.5 days; adding the same inspection stock again would double-count it.

Suppose the operator separately chooses 60 ready spare pallets outside that cycle as an initial planning assumption. The preliminary pool target is 600 + 60 = 660 pallets. The 60 is invented for illustration, not a recommended allowance or evidence of a particular availability level. The team must test whether the reserve covers the actual timing and variability of its operation.

If the site owns 500 pallets, of which 40 are permanently retired and cannot return to service, there are 460 usable pallets across the cycle and ready stock. A preliminary additional order is 660 − 460 = 200 pallets, subject to model compatibility, actual stock verification and project approval. Do not subtract pallets temporarily in inspection from usable inventory if their inspection time is already included in the cycle calculation; do not count retired units twice.

4. Test the assumptions before setting the order

The average does not tell you how many pallets are needed at the busiest hour or after a delayed return. Ask operations and the return partner for the distribution of turnaround times, shift patterns, peak arrivals, return schedules and inspection capacity. Map when pallets become ready against when loads need them; where actual records exist, test the proposed reserve against historical peaks and credible delays. A stock-flow projection should keep each pallet in only one location or status at a time.

For illustration only, if cycle starts remained at 240/day while the average cycle time increased from 2.5 to 3.0 days in a separate stable scenario, the circulating average would be 240 × 3.0 = 720 pallets, before reserve. This is a sensitivity calculation, not a prediction of the peak: throughput, delays and readiness can change together. Adjust the model when they do.

Decide separately how to replace pallets that are lost or permanently removed. Record actual losses and replenishment lead time; a one-off reserve assumption is not a perpetual replacement plan. Include purchase, return and preparation costs in the cost comparison without counting the same items twice.

5. Check the physical and project constraints

A calculated quantity still needs a feasible home and a compatible route. Check the maximum loaded and empty inventories, staging space and empty-return equipment with the site team. Include the actual maximum idle pallet arrangement in the fire protection review; an average pool estimate does not approve a stack height or storage location.

Before placing an order, agree the series, model, configuration and drawing revision, load and support conditions, conveyor and pickup interfaces, and representative sample acceptance with the equipment owner and pallet supplier. A sufficient pallet count cannot make an unverified pallet compatible with a rack or conveyor. See the sample testing checklist.

Prepare the purchase request

Share the route and cycle boundary, calendar or working-day basis, average and peak demand records, average return and preparation times, proposed ready reserve, usable stock by configuration and any loss or replenishment assumptions. Mark estimates and missing measurements clearly. Contact BAOHENG to discuss candidate configurations, quantity, available drawings and sample arrangements. The site remains responsible for its pool sizing, equipment approval and storage plan.

Sources and scope

Sources reviewed 23 November 2026. The example values and reserve are hypothetical; no specific site result, product performance or service level is claimed.